Scooby2beDue [name of document]

Spring Quarter 1996
4/07/96

Document Author:

Jason "Jay" Pierce

Project Sponsors:

Gregory Abowd

Scooby2beDue Team:

Jon A. Preston (Technincal Writer)
Ken Griggs (Architect)
Tony Saladino (Programmer)
Minh Ho (Programmer)
Jason Pierce (Manager/Technical Writer)



Original Project Schedule

as of April 19, 1996

Dates -4/1- -4/8- -4/15- -4/22- -4/29- -5/6- -5/13- -5/20- -5/27- -TOTALS-
Meetings 10 19 8 5 10 5 5 10 5 77
Documentation 2 10 10 10 10 10 10 10 5 77
Design 0 4 12 8 3 0 0 0 0 27
Training 45 28 18 0 0 0 0 0 0 91
Coding 0 7 18 35 35 20 10 0 0 125
Debugging 0 0 0 0 5 15 20 0 0 40
Integration 0 0 0 0 0 5 5 10 0 20
System Testing 0 0 0 0 0 0 12 12 6 30
MILESTONES Project Teams Project Plan Requirements Document Design Document Final Demo Final Notebook
TOTALS 57 68 66 58 63 55 62 42 16 487


Scooby2beDue Home Page
Last Modified 04/25/96 -- Jay Pierce (gt5731d@prism.gatech.edu)