Weekly Report on Project Status

Course: CS3302 (Spring 1996)

Week ending: (05/19/96)



Group Name: Scooby2bedue


Group Members
Name Role Attendance
Jay Pierce Manager, Technical Writer
 
Jon Preston Technical Writer
 
Ken Griggs Architect
 
Minh Ho Programmer
 
Tony Saladino Programmer
 


Progress

5th status report

Design Work - done
Requirements - version 2 completed
Design Doc - version 2 completed
Implementation - ongoing; dialogue boxes work
Debugging/Integration - continued
Research - done
Project Plan - updated
Training - continuous
RemoteFile - complete
Demo2 - completed

Updated Project Schedule

Dates -4/1- -4/8- -4/15- -4/22- -4/29- -5/6- -5/13- -5/20- -5/27- -TOTALS-
Meetings 10 19 8 10 10 5 5 10 5 82
Documentation 2 10 10 5 12 7 10 10 5 71
Design 0 4 12 3 7 10 0 0 0 36
Training 45 28 18 0 0 0 0 0 0 91
Coding 0 7 18 24 28 37 10 0 0 124
Debugging 0 0 0 0 2 9 20 0 0 31
Integration 0 0 0 0 0 0 5 10 0 15
System Testing 0 0 0 0 0 0 12 12 6 30
MILESTONES Project Teams Project Plan Requirements Document Design Document Final Demo Final Notebook
TOTALS 57 68 66 42 59 68 62 42 16 480


Original Project Schedule

as of April 19, 1996

Dates -4/1- -4/8- -4/15- -4/22- -4/29- -5/6- -5/13- -5/20- -5/27- -TOTALS-
Meetings 10 19 8 5 10 5 5 10 5 77
Documentation 2 10 10 10 10 10 10 10 5 77
Design 0 4 12 8 3 0 0 0 0 27
Training 45 28 18 0 0 0 0 0 0 91
Coding 0 7 18 35 35 20 10 0 0 125
Debugging 0 0 0 0 5 15 20 0 0 40
Integration 0 0 0 0 0 5 5 10 0 20
System Testing 0 0 0 0 0 0 12 12 6 30
MILESTONES Project Teams Project Plan Requirements Document Design Document Final Demo Final Notebook
TOTALS 57 68 66 58 63 55 62 42 16 487


Problems

Since last status report:

Development

Sockets are not completely unrestricted under appletviewer.
Dialogue boxes do not size properly.

Scheduling

Other classes and responsibilties are still demanding our time. (i.e. employers, other projects/homework).

No other problems to report.


Plans

Ken will be working with Minh and Tony to implement the following items: All of us will be contributing to the debugging and Prototype preparations efforts.

Other Comments



Project team remarks