All material is due by 7pm of day specified unless otherwise mentioned.
Material should be submitted electronically to ammar@cc.gatech.edu
Include CS8803 in subject line.
- Jan 22: Milestone 1 Topic and Team
- Feb 12: Milestone 2 Project Proposal
- March 6: HW given
- March 13: HW due
- April 3: Milestone 3 Project Progress Report
- April 8: Test
- April 14 (5pm): Power Point presentation due (tentative and may be moved up)
- April 15, 17, 22, 24: In-class presentations (tentative -- more dates may be added)
- April 28 (midnight): Final project report due.