Course: CS3302 (Spring 1996)
Instant Finance Group | |
Name | Title |
Brian Leslie | Manager |
Dedrick Duckett | Architect |
David Daniel | Technical Writer |
Geoff Menegay | Programmer |
Jason Pastor | Programmer |
ACTIVITIES | hours per week | Planned Total | Actual Total | ||||||||
Meetings | 7 | 10 | 8 | 10 | 5 | 5 | 7 | 12 | 7 | 68 | 71 |
Requirements | 5 | 2 | 15 | 2 | 6 | 25 | 30 | ||||
Documentation | 5 | 7 | 18 | 10 | 13 | 5 | 15 | 10 | 15 | 73 | 98 |
Training | 40 | 15 | 18 | 5 | 7 | 9 | 50 | 94 | |||
Preliminary Design / Prototyping |
5 | 17 | 3 | 3 | 5 | 6 | 25 | 39 | |||
Detailed Design | 5 | 10 | 6 | 25 | 21 | ||||||
Coding | 15 | 2 | 10 | 30 | 15 | 20 | 70 | 92 | |||
Pre-Integration Testing |
.5 | 8 | 8 | 25 | 16.5 | ||||||
Integration | 1 | 10 | 20 | 35 | 31 | ||||||
Post-Integration Testing |
10 | 10 | 5 | 100 | 25 | ||||||
Modification / Enhancements |
2 | 30 | 2 | ||||||||
MILESTONES | Project Teams | Project Plan | Requirements Document |
Design Document | Final Demo | Project Notebook | |||||
Apr. 3 | Apr. 8 | Apr. 22 | May 6 | May 20-22 | May 29 | ||||||
DATE | April | May | |||||||||
1 - 7 | 8 - 14 | 15 - 21 | 22 - 28 | 29 - 5 | 6 - 12 | 13 - 19 | 20 - 26 | 27 - 2 | |||
Planned Totals | 62 | 62 | 62 | 70 | 62 | 67 | 62 | 57 | 22 | 526 | |
Actual Totals | 62 | 71.5 | 64 | 40 | 84 | 57 | 62 | 52 | 27 | 519.5 |