Final Status Report

Course: CS3302 (Spring 1996)


Group Name: Instant Finance

Group Members:

Instant Finance Group
Name Title
Brian Leslie Manager
Dedrick Duckett Architect
David Daniel Technical Writer
Geoff Menegay Programmer
Jason Pastor Programmer



Project Schedule Comparison

ACTIVITIES hours per week Planned Total Actual Total
Meetings 7 10 8 10 5 5 7 12 7 68 71
Requirements 5 2 15 2 6 25 30
Documentation 5 7 18 10 13 5 15 10 15 73 98
Training 40 15 18 5 7 9 50 94
Preliminary Design /
Prototyping
5 17 3 3 5 6 25 39
Detailed Design 5 10 6 25 21
Coding 15 2 10 30 15 20 70 92
Pre-Integration
Testing
.5 8 8 25 16.5
Integration 1 10 20 35 31
Post-Integration
Testing
10 10 5 100 25
Modification /
Enhancements
2 30 2
MILESTONES Project Teams Project Plan Requirements
Document
Design Document Final Demo Project Notebook
Apr. 3 Apr. 8 Apr. 22 May 6 May 20-22 May 29
DATE April May
1 - 7 8 - 14 15 - 21 22 - 28 29 - 5 6 - 12 13 - 19 20 - 26 27 - 2
Planned Totals 62 62 62 70 62 67 62 57 22 526
Actual Totals 62 71.5 64 40 84 57 62 52 27 519.5


Progress:



Problems:


Plans: