Project Description

Important Client Deadlines

Tentative 1996 Winter Quarter Project Schedule

Explanation of Activities


PROJECT DESCRIPTION

Yakko Wakko and Dot Profile (YWD Profile) project team is a subgroup of the Java as Desktop project. Our project is focused on building a Java calendar browser applet. The College of Computing currently uses two calendar programs: Now Up-to-Date and the X utility "plan". The Now Up-to-Date application runs on MacIntosh platform while the "plan" utility runs on Unix workstations. People with accounts in the College of Computing have the option to create a publicly readable calendar file. Our Java calendar applet must be able to read and display the information in the calendar file, allow updates to the calendar from Java, and be able to browse other people's calendar and schedule appointments.

There are several precursor systems that attempts to do the same tasks. This project team will study these other works to gain insight on the inner-working and pros and cons of the system. By studying the existing systems we will be able to create a new system that is an improvement from the existing ones. The precursor systems to be studied are: Netscape Calendar, DISCS, and previous Java Prototypes.

The Netscape Calendar was created by a College of Computing undergraduate. The application uses Hypertext Markup Language along with Perl to produce a browse-able calendar on Netscape. DISCS is a continuing project as part of the Real-World Lab (CS 4310/1/2) that implements a calendar system for the Office of Information Technology (OIT). Several College of Computing graduates have done initial Java prototypes for an edit-able calendar.

Many of the previous systems that we are going to study are written in HTML. The limited functions in HTML places many constraints on what the system can provide. Building a calendar program with Java applets provides us with more functionality and options. With the more powerful Java applet, the new calendar will be a vast improvement from previous systems.

We have discovered that a College of Computing graduate student named Anind Dey is also doing a similiar project with us. With Dr. Abowd's approval, Anind has joined our group and will work as the third programmer for this project. Anind is joining our group at the beginning of our development (when we are learning Java). Being able to train and work with us from the very beginning, Mr. Dey will be a great asset to our project team.


Important Client Deadlines
Part to Turn in Deadline General Description
Project Plan January 12th, 1996 o Team introduction
o Project schedule
o Explanation of activities
o Brief project description
Requirements Document January 29th, 1996 o List of functional activities
o Storyboard
Design Document February 9th, 1996 o Describe how the system is implemented
Initial Prototype February 23th, 1996 o Cool looking Java calendar
Final Project Notebook March 3rd, 1996 o Software ready to ship and sell


Tentative 1996 Winter Quarter Project Schedule
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4
Learning Java xxxxx
Requirement Gathering xxxxx
Create Goals xxxxx
Requirements Document xxxxx
Brainstorm xxxxx
Design Document xxxxx
Design Review xxxxx
Final Design xxxxx
Module Implementations xxxxx
Component Testing xxxxx
Component Debugging xxxxx
Component Re-Testing xxxxx
Component Revision xxxxx
System Integration xxxxx
System Testing xxxxx
System Debugging xxxxx
System Re-Testing xxxxx
System Revision xxxxx


EXPLANATION OF ACTIVITIES

Learning Java (60 hours)

Description:

We will be developing a prototype using Java applets. The applets will be executable within both Java browsers and Netscape 2.0bx browsers. All members of the team will be engaged in this activity. The programmer and architect will spend most of their time learning the applet language and gathering tutorial materials to build up their experience. The programmers will then hold a training session for the remaining project team members.

Roles:

Architect (10 hrs), Programmers (45 hrs), Manager (2.5 hrs), Writer (2.5 hrs)

Deadline/Special Notes

January 22, 1996. The training session will be on the team meeting date, which is January 30th, 13:00 at CoC202.


Requirements Gathering (10 hours)

Description:

We will be conducting interviews with the stakeholder (in this case, Dr. Abowd) to gather requirements for the system.

Roles:

Architect (5 hrs), Manager (2.5 hrs), Writer (2.5 hrs)

Deadline/Special Notes

January 24, 1996.


Create Goals (5 hours)

Description:

The manager will create goals for the system. The list of goals will dictate the essentials for the system and, if time allows, options and extra functionality that may make the system more useable and/or powerful. The obstacles and constraints will be considered.

Roles:

Manager (4.5 hrs), Writer (0.5 hrs)

Deadline/Special Notes

January 26, 1996.


Requirements Document (40 hours)

Description:

The requirements document will specifies what the system will do and functionalities that the system will have. The document will also give scenarios and storyboards on the behavior of the system. This is what the system will be build on.

Roles:

Architect (20 hrs), Programmers (5 hours), Manager (5 hrs), Writer (10 hrs)

Deadline/Special Notes

Projected Deadline: January 27, 1996.
Client Due Date: January 29, 1996.


Brainstorm (8 hours)

Description:

The manager and architect will brainstorm on possible functions for the calendar.

Roles:

Manager (3 hrs), Architect (3.5 hrs), Writer (0.5 hrs)

Deadline/Special Notes

January 29, 1996.


Design Document (96 hours)

Description:

The design document will give specific description on the functionality of various modules. How the modules link to other modules will be display in graphical form. The programmers will base their implementation on the design document to ensure coherence among the different modules that will be written by different programmers.

Roles:

Architect (40 hrs), Programmer (30 hrs), Manager (6 hrs), Writer (20 hrs)

Deadline/Special Notes

Projected deadline: February 6, 1996.
Client Due Date: February 9, 1996.


Design Review (20 hours)

Description:

The whole team will review the design that decide if there should be any changes. This is the last chance to do any significant design changes.

Roles:

Architect (5 hrs), Programmers (10 hrs), Manager (3 hrs), Writer (2 hrs)

Deadline/Special Notes

February 9, 1996.


Final Design (10 hours)

Description:

This is after the design document is turned in to the client and changes will be made to the design document according to the client`s suggestion.

Roles:

Architect (5 hrs), Writer (5 hrs)

Deadline/Special Notes

February 12, 1996.


Module Implementations (90 hours)

Description:

With the design document finalize, the programmers will implement the modules specified in the design document. The architect will coordinate the assignment and the manager will oversee the project. The writer will keep note of the problems that the programmers encountered in order to document it.

Roles:

Architect (10 hrs), Programmer (60 hrs), Manager (10 hrs), Writer (10 hrs)

Deadline/Special Notes

Projected Deadline: February 19, 1996.
Client Due Date: February 23, 1996.


Component Testing (10 hours)

Description:

The programmers will test the components with various data sets to uncover problems with modules.

Roles:

Programmer (10 hrs)

Deadline/Special Notes

February 19, 1996.


Component Debugging (20 hrs)

Description:

The programmers will fix problems that might exist in the program. At this stage, the modules should be almost complete except with the exception of problems with selected test sets.

Roles:

Programmer (20 hrs)

Deadline/Special Notes

February 21, 1996.


Component Re-Testing (10 hours)

Description:

After the "bugs" are detected and fixed, there should be another test phrase to make sure no addition bugs appears. Fixing one problem of a program might result in another problem, this phrase is used to eliminate additional problems.

Roles:

Programmers (10 hrs)

Deadline/Special Notes

February 24, 1996.


Component Revision (12 hrs)

Description:

This is the last stage of the component test phrase. The architect will work with the programmer to make sure the components are implemented according to the design document and that different components are compatible when put with each other.

Roles:

Architect (2 hrs), Programmers (10 hrs)

Deadline/Special Notes

February 26, 1996.


System Integration (20 hrs)

Description:

The architect will assist the programmers in integrating the various components together. The writer will be present to document any difficulties the team might encounter. The modules will be put together and will work as a whole.

Roles:

Architect (5 hrs), Programmers (10 hrs), Writer (5 hrs)

Deadline/Special Notes

February 29, 1996.


System Testing (10 hrs)

Description:

After the modules are integrated, sample test data must be runned to make sure the modules behave as they were when it was independent. Addition problems regarding integration might be detected.

Roles:

Programmer (10 hrs)

Deadline/Special Notes

March 1, 1996.


System Debugging (30 hours)

Description:

The system testing phrase will most likely uncover additional bugs that were not detected earlier. This is the last chance for the programmers to detect bugs that exists in the system and bugs that might arise from the integration of various modules.

Roles:

Architect (5 hrs), Programmer (15 hrs), Manager (5 hrs), Writer (5 hrs)

Deadline/Special Notes

March 4, 1996.


System Re-Testing (20 hours)

Description:

The programmers will fix many bugs in the debugging phrase. This phrase is used to re-test the system to make sure that no additional bugs appears because of the previous phrase.

Roles:

Programmers (20 hrs)

Deadline/Special Notes

March 6, 1996.


System Revision (20 hours)

Description:

Problems detected in the re-test phrase will be corrected in the revision phrase. This phrase corrects any last minute problems that might appear.

Roles:

Architect (5 hrs), Programmers (15 hrs), Manager (5 hrs), Writer (5 hrs)

Deadline/Special Notes

March 11, 1996.