Winter Quarter 1996 February 12, 1996
Document Author:
Project Sponsor:
| Yakko Wakko and Dot Profile Team:
Manager: Harry Marlin |
Training Activities | ||||||||
---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
Learning Java | P: 9 A: 1 | P: 9 A: 1 | P: 9 A: 1 |
Requirements Activities | ||||||||
---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
Requirement Gathering | A: 2 M: 2 T: 5 | A: 2 M: 2 T: 5 | ||||||
Create Goals | A: 1 | A: 1 T: 3 |
Design Activities | ||||||||
---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
Brainstorm | A: 5 M: 1 T:5 | |||||||
Design Review | A: 5 M: 1 T: 10 | |||||||
Final Design | A: 5 M: 1 T: 10 |
Component Testing Activities | ||||||||
---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
Module Implementations | P: 13 | P: 12 | ||||||
Component Testing | P: 5 | P: 5 | ||||||
Component Debugging | P: 5 | P: 5 | ||||||
Component Re-Testing | P: 5 | |||||||
Component Revision | P:12 |
Systems Testing Activities | ||||||||
---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
System Integration | P: 2 A: 2 | |||||||
System Testing | P: 10 | |||||||
System Debugging | P: 15 | P: 15 | ||||||
System Re-Testing | P:20 | |||||||
System Revision | P:20 |