| Winter Quarter 1996 February 12, 1996
Document Author:
Project Sponsor:
| Yakko Wakko and Dot Profile Team:
Manager: Harry Marlin |
| Training Activities | ||||||||
|---|---|---|---|---|---|---|---|---|
| Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
| Learning Java | P: 9 A: 1 | P: 9 A: 1 | P: 9 A: 1 |
| Requirements Activities | ||||||||
|---|---|---|---|---|---|---|---|---|
| Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
| Requirement Gathering | A: 2 M: 2 T: 5 | A: 2 M: 2 T: 5 | ||||||
| Create Goals | A: 1 | A: 1 T: 3 |
| Design Activities | ||||||||
|---|---|---|---|---|---|---|---|---|
| Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
| Brainstorm | A: 5 M: 1 T:5 | |||||||
| Design Review | A: 5 M: 1 T: 10 | |||||||
| Final Design | A: 5 M: 1 T: 10 |
| Component Testing Activities | ||||||||
|---|---|---|---|---|---|---|---|---|
| Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
| Module Implementations | P: 13 | P: 12 | ||||||
| Component Testing | P: 5 | P: 5 | ||||||
| Component Debugging | P: 5 | P: 5 | ||||||
| Component Re-Testing | P: 5 | |||||||
| Component Revision | P:12 |
| Systems Testing Activities | ||||||||
|---|---|---|---|---|---|---|---|---|
| Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 |
| System Integration | P: 2 A: 2 | |||||||
| System Testing | P: 10 | |||||||
| System Debugging | P: 15 | P: 15 | ||||||
| System Re-Testing | P:20 | |||||||
| System Revision | P:20 |
|
|
|
|
|
|
|