Winter Quarter 1996 February 12, 1996
Document Author:
Project Sponsor:
| Yakko Wakko and Dot Profile Team:
Manager: Harry Marlin |
Training Activities | |||||||||
---|---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 | Total |
Learning Java | P: 9 A: 1 | P: 9 A: 1 | P: 9 A: 1 | P:27 A:3 | |||||
Total | P:9 A:1 | P:9 A:1 | P:9 A:1 | P:27 A:3 |
Requirements Activities | |||||||||
---|---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 | Total |
Requirement Gathering | A: 2 M: 2 T: 5 | A: 2 M: 2 T:5 | A: 2 M: 3 T:5 | A:5 | A:11 M:7 T:15 | ||||
Create Goals | A: 1 | A: 1 T: 3 | M:1 T:3 A:1 | A:1 T:3 | |||||
Total | A:3 M:2 T:5 | A:3 M:2 T:8 | A:2 M:3 T:5 | A:1 M:1 T:3 | A:5 | A:12 M:7 T:18 |
Design Activities | |||||||||
---|---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 | Total |
Brainstorm | A: 5 M: 1 T:5 | M: 2 T:2 | A:5 M:3 T:7 | ||||||
Design Review | A: 5 M: 1 T: 10 | T:4 | A:5 M:1 T:14 | ||||||
Final Design | A: 5 M: 1 T: 10 | A:5 T:8 | A:10 M:1 T:18 | ||||||
Total | A:5 M:1 T:5 | A: 10 M: 2 T: 20 | A:5 M:2 T:14 | A:20 M:5 T:39 |
Component Testing Activities | |||||||||
---|---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 | Total |
Module Implementations | P: 13 | P: 12 | P: 10 | P:10 | P:45 | ||||
Component Testing | P: 5 | P: 5 | P: 5 | P:5 | P:4 | P:24 | |||
Component Debugging | P: 5 | P: 5 | P: 5 | P:5 | P:20 | ||||
Component Re-Testing | P: 10 | P:10 | P:20 | ||||||
Component Revision | P:15 | P:2 | P:5 | P:22 | |||||
Total | P:13 | P:22 | P:30 | P:25 | P:32 | P:9 | P:131 |
Systems Testing Activities | |||||||||
---|---|---|---|---|---|---|---|---|---|
Activities | Jan 15 | Jan 22 | Jan 29 | Feb 5 | Feb 12 | Feb 19 | Feb 26 | Mar 4 | Total |
System Integration | P: 2 A: 2 | P: 10 | P:2 | P:16 | |||||
System Testing | P: 15 | P:5 | P:2 | P:22 | |||||
System Debugging | P: 10 | P: 10 | P:5 | P:25 | |||||
System Re-Testing | P:5 | P:10 | P:3 | P:18 | |||||
System Revision | P:8 | P:20 | P:10 | P:38 | |||||
Total | A:2 P:2 | P:48 | P:45 | P:22 | P:119 |
Top | Plan | Req Doc | Design Doc | Prototype | History | Revision |