CS3302 Schedule

Yakko Wakko and Dot Dayplan

Project Schedule Version 6 (March 3rd 1996)


Winter Quarter 1996
February 12, 1996

Document Author:
Eugene Liang

Project Sponsor:
Gregory Abowd

Yakko Wakko and Dot Profile Team:

Manager: Harry Marlin
Architect: Tom Moss
Programmer: Mark Canup
Programmer: Roy Rodenstein
Programmer: Anind Dey
Technical Writer: Eugene Liang


Training Activities
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4Total
Learning Java P: 9
A: 1
P: 9
A: 1
P: 9
A: 1
P:27
A:3
TotalP:9
A:1
P:9
A:1
P:9
A:1
P:27
A:3

Requirements Activities
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4Total
Requirement Gathering A: 2
M: 2
T: 5
A: 2
M: 2
T:5
A: 2
M: 3
T:5
A:5A:11
M:7
T:15
Create Goals A: 1A: 1
T: 3
M:1 T:3 A:1A:1
T:3
TotalA:3
M:2
T:5
A:3
M:2
T:8
A:2
M:3
T:5
A:1
M:1
T:3
A:5A:12
M:7
T:18

Design Activities
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4Total
Brainstorm A: 5
M: 1
T:5
M: 2 T:2A:5
M:3
T:7
Design Review A: 5
M: 1
T: 10
T:4A:5
M:1
T:14
Final Design A: 5
M: 1
T: 10
A:5 T:8A:10
M:1
T:18
TotalA:5
M:1
T:5
A: 10
M: 2
T: 20
A:5
M:2
T:14
A:20
M:5
T:39

Component Testing Activities
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4Total
Module Implementations P: 13P: 12P: 10P:10P:45
Component Testing P: 5P: 5P: 5P:5P:4P:24
Component Debugging P: 5P: 5P: 5P:5P:20
Component Re-Testing P: 10P:10P:20
Component Revision P:15P:2P:5P:22
TotalP:13P:22P:30P:25P:32P:9P:131

Systems Testing Activities
Activities Jan 15 Jan 22 Jan 29 Feb 5 Feb 12 Feb 19 Feb 26 Mar 4Total
System Integration P: 2
A: 2
P: 10P:2P:16
System Testing P: 15P:5P:2P:22
System Debugging P: 10P: 10P:5P:25
System Re-Testing P:5P:10P:3P:18
System Revision P:8P:20P:10P:38
TotalA:2
P:2
P:48P:45P:22P:119


Top Plan Req
Doc
Design
Doc
Prototype History Revision

Last modified: March 3, 1996 by Eugene Liang (eugene@cc.gatech.edu)